
| ASPECTS | DETAILS |
|---|---|
| Case Title | M/s. C & C Constructions Ltd. vs. IRCON International Ltd. (2025 INSC 138, Civil Appeal No. 6657 of 2023) |
| Introduction | The case concerns a dispute between M/s. C & C Constructions Ltd. and IRCON International Ltd. over a contract for constructing five Road Over Bridges (ROBs) in Rajasthan. The appellant sought compensation for delays allegedly caused by the respondent, while the respondent relied on Clause 49.5 of the General Conditions of Contract (GCC) to deny liability. |
| Factual Background | A contract was signed on June 28, 2012, for constructing five ROBs. The appellant claimed the respondent caused delays, leading to financial burdens. Time extensions were granted, and the appellant provided undertakings not to claim extra compensation. The arbitration tribunal rejected the claims based on Clause 49.5 of GCC, which barred compensation for employer-caused delays. The appellant challenged this decision before the Delhi High Court, which upheld the rejection. The matter was further appealed to the Supreme Court. |
| Legal Issues |
|
| Applicable Law |
|
| Analysis | The Supreme Court examined whether Clause 49.5 barred compensation claims and found that the appellant had repeatedly sought time extensions under this clause without reserving rights to compensation.The appellant’s explicit undertakings in 2015 to not claim compensation beyond escalation costs estopped them from later making claims.The court rejected the argument that the respondent waived Clause 49.5, emphasizing that contract terms were followed, and no contrary conduct was shown.The Delhi High Court correctly applied the limited review powers under Sections 34 and 37 of the Arbitration Act. |
| Conclusion | The Supreme Court upheld the rejection of the appellant’s claims, ruling that Clause 49.5 was enforceable and that the appellant was bound by its undertakings. The appeal was dismissed. |
| Current Scenario | The Supreme Court’s ruling reinforces the enforceability of liability limitation clauses in contracts and upholds arbitral autonomy, restricting judicial interference under Sections 34 and 37 of the Arbitration Act. It sets a precedent on contractual estoppel in arbitration cases. |
CASE SUMMARY – In this case M/s. C & C Constructions Ltd. entered into a contract with IRCON International Ltd. to construct five Road Over Bridges in Rajasthan. The appellant claimed compensation for employer-caused delays, which IRCON denied based on Clause 49.5 of the contract. The arbitration tribunal, Delhi High Court, and ultimately the Supreme Court upheld this clause, ruling that it barred compensation claims. The court emphasized that the appellant had sought time extensions under Clause 49.5 and provided undertakings not to claim extra compensation. The appeal was dismissed, affirming that contractual terms limiting liability are enforceable and reinforcing judicial non-interference in arbitration.
“A party that consciously elects to adhere to contractual provisions and expressly waives its right to claim damages cannot later contest the validity of those very provisions. The sanctity of contracts and the principle of estoppel bar such retrospective claims, ensuring certainty in commercial transactions.”
SOURCE – SUPREME COURT OF INDIA
READ ALSO – SC ON LEGAL SCRUTINY OF SUMMONING ORDERS IN CRIMINAL PROCEEDINGS





